Kernkraftwerk Leibstadt - Umbau Laborgebäude (ZM3)

Building automation for the conversion of a laboratory building

Kernkraftwerk Leibstadt - Umbau Laborgebäude (ZM3)
150
Data points
50
Field devices
2
Substations
2018 - 2021
Period
Building owner
Kernkraftwerk Leibstadt AG
General planner / HVAC and plumbing
Kernkraftwerk Leibstadt AG

GEA services

  • Planning of primary plant automation
  • Planning of room automation
  • Planning of conversion of existing systems
  • SIA Phases 31-53
  • Organisation / management of the integral test

Project description

The existing ZM3 buildings, which have served as a cold laboratory and cooling tower control room since the power plant was commissioned in 1984, showed a need for refurbishment and extension after 30 years of use. Cost-effective, sensible measures to preserve the value of the building fabric were implemented.

Building automation concept

As part of the renewal of the laboratory rooms, the various building services systems were also newly installed. A new automation station provides the necessary negative pressure in the laboratory rooms. The building automation planner also took on aspects of the technical coordination and the organisation of the integral test.