← All references Industry · Building automation

EWZ Unterwerk Zeughaus

Building automation for critical energy infrastructure

EWZ Unterwerk Zeughaus
1,200
Data points
250
Field devices
2
Substations
2022 - 2025
Period
Building owner
Elektrizitätswerk der Stadt Zürich (ewz)
General planner / HVAC and plumbing
Gähler und Partner AG

GEA services

  • Planning of primary plant automation
  • SIA Phases 31-53
  • Development of the building automation concept
  • Execution of market analysis for control systems
  • Development of new system guidelines for substations
  • Specialist site supervision and quality assurance
  • Technical coordination

Project description

The Zeughaus substation, a key infrastructure facility of the ewz grid in Zurich, was comprehensively modernised. The focus of the measures was the renewal of the entire control and building automation technology. In parallel, a standardised concept for future control systems in substations was developed and introduced for the first time.

Building automation concept

As part of the project, GEA Ingenieure AG took on the complete planning of the new building automation as well as the development of a forward-looking system standard for substations. A new standard architecture for future control systems was defined together with the building owner.